1. Overall Objective Produce v1.0.0-rc, the first client’s cutover plan, and the public open-source release.

2. The Problem We Are Solving Going live must be a reversible, criteria-driven decision, not a deadline.

3. Concepts and Research

  • Go/no-go criteria.
  • Cutover patterns: flip the authoritative ledger behind a flag, with the old ledger becoming the shadow for a period so rollback is possible.
  • Semantic versioning.
  • Open-source governance (contributing guide, code of conduct, licence).

4. Implementation Tasks

  • Cutover plan:
    1. Freeze window.
    2. Final replay check.
    3. Flip the flag.
    4. Old ledger becomes the shadow.
    5. Rollback trigger conditions and procedure.
  • Write the go/no-go criteria.
  • Tag v1.0.0-rc.1.
  • Public repo hygiene: README, LICENSE, CONTRIBUTING, SECURITY, architecture docs, examples.

5. Testing Requirements

  • Rehearse the cutover and the rollback twice in staging.

6. Deliverables Release candidate, cutover plan and the public release.

7. Acceptance Criteria Cutover and rollback rehearsed successfully, and the go/no-go criteria agreed.

8. Dependencies All weeks.

9. Estimated Difficulty Medium.

10. Exit Gate The cutover happens only when the go/no-go criteria are met, which may be after step 4.04. Shadow mode should have run at least 30 clean days before the flip.